Walk to the end of Pine Avenue on a weekday morning and you'll see Tampa Bay Marine crews still working the boat landing, laying the last stretches of decking onto a walkway that, from where you're standing, looks essentially whole. It's tempting to read that as "almost open." Most residents who've watched this project for two years have made that same leap at least once. It's the wrong read, and understanding why tells you more about how this rebuild actually works than any press release will.
The concrete work and the reopening date are running on two separate clocks. One of them has basically stopped. The other one hasn't started yet.
What actually got finished this summer
The walkway itself is close to done. Tampa Bay Marine, the Gibsonton-based contractor the city hired to rebuild the structure, spent July laying decking on the boat landing, the section that connects Pine Avenue to the pier proper. That decking sits on 800 feet of concrete slab, epoxied and rebar-tied into the pilings below, then topped with Kebony, a modified Norwegian pine the city selected because it stays cooler underfoot than composite alternatives. The whole rebuild, walkway included, is running around $8 million, with FEMA covering close to half and the rest split between Manatee County, the state, and the city.
That's a real, visible, mostly finished piece of infrastructure. It's also only half the project.
Why a finished walkway doesn't mean an open pier
Mayor Mark Short told The Islander on July 10 that the city was still finalizing logistics with Tangerine Group, an Anna Maria-based contractor, for demolition and remediation work at the T-end, the building complex at the far end of the pier where the walkway leads. As of that report, that work hadn't started. The plan is to open the shell of the T-end's southern building by swapping walls and windows for sliding glass doors, which is a different scope of work entirely from pouring slabs and driving pilings, and it runs on a different timeline with a different crew.
This is the part that's easy to miss if you're only watching from Pine Avenue. The walkway contract has a clear finish line that Tampa Bay Marine has been visibly closing in on for months. The T-end work doesn't have that same momentum yet, because it couldn't start until the city settled a much slower-moving question: who's actually going to run the building once it's fixed.
The tenant question took longer than the concrete
For nearly two years, the T-end's larger building sat empty. Mote Marine Laboratory had operated an education and outreach center there before the 2024 hurricanes, but the city and Mote mutually agreed to end that lease in January 2026, after what Short described as months of talks. That left the city with a vacant building and no clear plan, which is why officials held a public workshop that same month to ask residents what they wanted there. Suggestions ranged from a sunrise coffee shop to, in one resident's words at the meeting, "an old Florida crab shack-style seafood joint."
"We lost Annie's, we lost Rod & Reel Pier. Bring back the old AMI and say no to any more rip-offs." — Vicki Hart, Bradenton resident, at the January 2026 pier workshop
What the city landed on, five months later, was neither a coffee shop nor a new outside operator. It was the same family that had run the T-end's smaller building for years, expanding into the bigger space under a new name and a very different deal.
PIERadise is a bigger operation than the pier lost
Anna Maria commissioners voted unanimously on June 11, 2026 to approve a five-year lease with GSM Partners, owned by Brian Seymour, Benjamin Sato, and Jason Sato, to take over the larger east-side building at the T-end, which is the space Mote vacated. The company will operate under a new name, PIERadise, and the lease terms look nothing like what the same operators were paying before the storms.
| Old arrangement (through Dec. 2025) | New PIERadise lease (approved June 2026) | |
|---|---|---|
| Space | Smaller building, north side of T-end | Larger building, east side, former Mote outreach center |
| Rent | About $400 per square foot, per Seymour's 2025 disclosure to commissioners | $12,000 flat per month, plus utilities and CPI-indexed taxes |
| Term | Original five-year lease | Five years, with a 60-month extension option |
| Permitted use | Grill, bait, and tackle only | Grill, bar (beer and wine), and bait and tackle, in an expanded footprint |
Mayor Short called the new deal "very fair" during the June 11 meeting, adding that it could save the city several thousand dollars a month in avoided costs. GSM is also putting up $10,000 toward converting the building's shell into hurricane-rated sliding doors or a garage-door-style opening, and under the new lease the company takes on maintenance for all areas of the T-end.
That's the piece of the story that doesn't show up if you're only tracking concrete pours. The pier that reopens this fall isn't a repaired version of the one that closed in 2024. It's a larger single operation, under one lease, with more space to serve people than existed before the storms.
What's finished and what isn't, based on the latest reporting
If you want a quick way to track this yourself the next time you walk Pine Avenue, here's where things stood as of the most recent updates in mid-July:
- Finished or nearly finished: the walkway's structural slab, most of the decking, the boat landing work
- Not yet started as of mid-July: T-end demolition and remediation, the sliding-door conversion, utility hookups inside the T-end buildings
- Settled but not yet built out: the PIERadise lease, signed and approved, but the space itself is still an empty shell
The walkway finishing on schedule is genuinely good news. It's just not the milestone that determines when you can walk to the end and get a beer. That milestone is Tangerine Group's remediation work, which hadn't begun as of the most recent reporting, and PIERadise's build-out inside a shell that still needs new doors and power before anyone can open for business.
Why this matters if you live here
This is the pier's sixth rebuild since the original 1911 structure went up, following storm damage in 1921, 1935, 1974, 1988, and 2017. The last version reopened in 2020 and lasted four years before Helene and Milton took it apart again. That history is part of why the city has been deliberate, maybe slower than anyone would like, about getting the T-end lease right this time instead of just rushing a tenant back into the same footprint.
Hometown Desserts, which sits at the end of Pine Avenue and has drawn pier foot traffic for 16 years, is one of several nearby businesses waiting on the reopening to bring that traffic back. When PIERadise opens, it'll be doing it from a bigger space with a longer lease than the operation the island lost, which is a different kind of return than most people picture when they see the decking going in.
So the next time you're walking past the construction fencing and the deck looks done, it's worth remembering that the concrete stopped being the obstacle months ago. Watch for scaffolding at the T-end instead. That's the part that tells you when this is actually over.
If you're the kind of person who tracks what's happening in your own neighborhood this closely, you're probably also curious what it means for your home's value when the landmark down the street reopens bigger than it was before. Renne' Rupp works with owners across Anna Maria Island who want that kind of read on their own property. Request a Free Home Valuation whenever you're ready to see where things stand.
Published August 6, 2026. Local conditions, rules and prices change; details reflect information available at the time of publication and are for general information only, not legal, tax or financial advice.